The project scope of work includes roadside ditch and side drain restoration for the following roads: Pettie Road (2,000± Linear Feet (LF)), Haynes Road (1,500± LF), Montayne Avenue (1,000± LF), Brag Street (1,000± LF), Franklin Avenue (1,000± LF), and Lindsey Street (3,500± LF). This project includes approximately 2,000 cubic yards of earthwork (manipulation of soil and rock) to restore approximately 2-miles of roadside ditches. The project will also replace 6,288 linear feet (LF) of 12"x23" side drain pipes, 80 LF of 19"x30" side drain pipes, 25 ditch bottom inlets, 8 manholes, 254 mitered end sections, and approximately 135 driveway.

Community Benefit

The primary objective of this project is to implement a drainage improvement solution that will facilitate conveyance of stormwater runoff that will reduce flooding peak and duration. This project will be carried out under the Infrastructure Program to address (1) known infrastructure deficiencies, (2) provide mitigation and resilience measures to better protect infrastructure from increased frequency and severity of storm events, and (3) align with the County’s long-term recovery and resiliency strategy.

Total Amount BOCC Approved:
$3,900,000.00

Project Status:
Approved

HUD National Objective:
LMI/LMA

Default Image
Project Photo Coming Soon

Project Location(s)

Project Location(s)
Address Anticipated Construction Start Date Anticipated Construction End Date
Pettie Rd, Dover, FL 03/31/2028